Week Twenty-Nine
Will start February 25, 2020
54
0
0
We are in Week 29 of the Shelter Renovations, and shower stalls are being installed, the conference room is taking shape, and a majority of the painting of the walls upstairs is complete.
We are in Week 29 of the Shelter Renovations, and shower stalls are being installed, the conference room is taking shape, and a majority of the painting of the walls upstairs is complete.